Project Overview
The building’s existing chilled water & LPHW systems were not providing comfortable conditions, were inefficient and reaching the end of their normal working life. Also, the building didn’t have any fresh air ventilation, apart from through openable windows. The Project involved removal of all existing services, followed by the installation of new Mitsubishi VRF systems to provide heating/cooling and Mitsubishi Lossnay units to provide fresh air. Existing Denco close control systems in the server room were replaced with Airedale Units. All works were done on night shifts to ensure zero impact on call centre operations.
Project Budget
£730,000.00
Main Contractor
Wates
Consultant
Temperature Control (D&B)
No. of Personnel
12 to 22
Project Description
Supply installation of Mitsubishi VRF systems & Mitsubishi Lossnay units to provide fresh air. Existing Denco close control systems in the server replaced with Airedale Units.