Project Overview
The New Data Centre was formed within a newly constructed purpose made Data Centre and office accommodation. High density blade server technology meant that the indoor units mainly comprised an APC InRow Rack Cooling Solution, along with some Airedale down flow traditional type cooling units connected to the chilled water system. Future expansion technology has been considered for business growth.
Project Budget
£233,169.00
Project Details
New Data Centre, Bristol
Project Description
Installation and commissioning of 3 No 80kW Aquasnap Liquid Chillers to serve the APC InRow Cooling Solution and Airedale chilled water down flow units. Along with a specialist underfloor water leak detection system and fault alarm panel interface system. Pipework method used was Georg Fischer COOL-FIT pre-insulated ABS.